Develop a Schedule and Budget 查看中文版
第 1 节
You start defining a project schedule during the buildup phase of the project management process. To define your project schedule, begin by determining the latest date for completing your project—a date that can't be changed. Work backward from that date to see when you and your team will need to provide interim deliverables.
Develop a Schedule and Budget
During the implementation phase, you will closely monitor the schedule you've created. If conditions change, you'll likely need to adjust your schedule.
Develop a Schedule and Budget
第 2 节
- Use the Work Breakdown Structure or a similar outline to develop a list of specific activities or tasks.
- Assign a deliverable to each activity—for instance, "rough draft of survey questions" or "prototype for test market" or "beta version."
- Use deliverables as a basis for creating a project schedule with realistic milestones and due dates.
- Identify bottlenecks that could upset the schedule.
- Determine ways to remove bottlenecks or build in extra time to get around them.
- Establish control and communication systems for updating and revising the schedule.
Make a Connection
第 3 节
Critically examine your draft schedule. Seek ways to make it more accurate, more realistic, and tighter. Look for:
-
Errors. Are your time estimates realistic? Pay particular attention to time estimates for tasks on the critical path. If any of these tasks cannot be completed on time, the entire schedule will unravel. Also, review the relationships between tasks. Does your schedule reflect tasks that can start simultaneously and those that can't start until some other task is completed?
-
Oversights. Have you left out any tasks or subtasks? Have you overlooked time for training and maintenance?
-
Overcommitments. Will some employees have to work 10 to 12 hours per day for months on end to complete the tasks assigned to them? Are you expecting a piece of equipment to perform in excess of its known capacity? If so, remove such overcommitments—for instance, by redistributing the workload.
-
Bottlenecks. Will work necessary for a particular task pile up at that point in the process? Think of an auto assembly line that has to stop periodically because the people who install the seats cannot keep up with the pace of the line. To remove bottlenecks, speed up the work process used in that task or shift resources into that task—for example, by adding people who have some slack time in their responsibilities.
Tips for scheduling your project
第 4 节
Managers use several different kinds of tools to create draft schedules. These include bar charts, flow charts, and PERT charts.
Bar charts
Bar charts show project stakeholders how a project is progressing. A Gantt chart is one example. A Gantt chart is simple and shows the "big picture" of a project at a glance. It lists project tasks in the left-hand column and indicates time blocks for each. These blocks indicate when each task should begin, based on task relationships, and when it should end.
Sample Gantt Chart
Gantt charts show the following:
-
Task status; completed tasks are shaded out
-
Estimated project duration
-
Estimated task duration
-
Task sequences and tasks completed in parallel
But Gantt charts don’t show task dependencies—that is, which task must be completed before another begins. Thus, these charts make it difficult to assess the impact of a change in one area on the rest of a project.
Flow charts
Flow charts help your team closely manage and communicate project details to your supervisors and project team members. A critical path diagram is one example. This kind of diagram shows your project's critical path: the set of tasks that determines total project duration. The critical path is the longest sequence of tasks through the project. Any delays in the critical path will delay completion of the entire project. By identifying the critical path for your project, you can allocate resources efficiently.
sample critical path diagram
PERT charts
A PERT (performance evaluation and review technique) chart shows when every project task within a phase should begin, how much time is scheduled for each task, and when each task should be completed. The chart also shows all tasks in progress at a given time and all the dependencies between outcomes, tasks, and events.
Sample Pert chart
In the PERT chart, each task is represented by a node that connects with other nodes, or tasks, required to complete the project. While a PERT chart indicates the important task dependencies of a project, a downside is that the chart can be complex and difficult to master.
无论多么有经验,你都需要一个项目计划 why you need a project plan
哈佛教授讲授视频逐字稿
Use scheduling tools flexibly
Choose the scheduling tool that best suits you and your project. You'll probably end up using different kinds of tools at different times, depending on whether you want to show:
-
What has to be done
-
How long a particular activity will take
-
In what order each activity has to happen
-
Who is responsible for each activity
Bar charts are good for showing stakeholders and end users how the project is progressing. Flow charts are good for closely managing and communicating detailed information to supervisors and people doing the work. PERT charts are good for showing important task dependencies.
But the best tool for managing a project is the one you're most comfortable with. Don't be lured into using a tool just because "everyone else does" or because it's "cutting-edge." To pick the best method for you, use your experience. Look at the system you use for tracking your own work, and consider how satisfied you are with it. That can help you decide whether to stay with your current system or try some new ones.
Tips for selecting project management software
第 5 节
A budget is the financial blueprint or action plan for your project. It translates the project plan into measurable expenditures and anticipated returns over a certain period of time. Your success as a project manager, as well as the success of your project itself, will be measured in part on whether you complete the project within the budget.
Creating your budget is something you do during the buildup phase of the project management process. However, you may have to adjust your budget during the implementation phase if circumstances change.
To develop your project budget, first ask yourself: What is it going to take—in terms of resources—to successfully complete this project? To determine the cost of the project, break it down into the key cost categories you anticipate.
Typical project costs
Identify the cost categories, also known as line items, relevant for your budget. Typical project cost categories include:
-
Personnel. This is almost always the largest part of a project's budget. It includes full-time and temporary workers.
-
Travel. People may have to travel from one location to another to do their project work. Consider whether everyone will be on-site, or whether the team will need to gather at one locale. Remember to budget for meals and lodging.
-
Training. If training will be required, determine whether it will take place on-site, or whether travel expenses will be involved. If you plan to hire an outside contractor to provide the training, make sure your budget reflects his or her fees and expenses.
-
Supplies. In addition to the usual—computers, pens, papers, software—you may need unique materials.
-
Space. If some people may have to be relocated to other facilities, estimate how much room and money that would require.
-
Research. Consider whether you'll have to buy studies or data to support your project versus your team performing such research itself.
-
Professional services. If you'll have to hire a market research firm, bring in a consultant, or seek legal advice, reflect those costs in your budget.
-
Capital expenditures. You may need equipment or technical upgrades to complete the project. Some of these capital expenditures will need to pay for themselves.
Review and refine the initial cost estimates you made during the planning phase of your project. And remember that a budget, no matter how carefully planned, is still just your best guess. Be prepared for actual numbers to deviate from your original estimates. And stay as flexible as possible within your limitations of time, quality demands, and total money available.
Often-overlooked costs
Consider often-overlooked costs that could affect your project budget. Examples include:
-
Training costs after the project is completed to teach users to implement your project
-
Ongoing personnel and maintenance costs once the project is complete
-
Insurance
-
Licensing fees
-
Costs for outside support such as accounting or legal counsel
Contingency funds
Many project budgets contain some degree of flexibility. That's because it's extremely difficult to anticipate every expense in a project. To give your budget some flexibility, build in contingency funds—for instance, you might ask for 5% of the estimated project budget for contingency alone. This allows you to accommodate some unanticipated costs without having to ask for more funding later.
Should your project proceed?
To build your project budget, you estimate costs before the work actually begins. So creating the budget gives everyone a chance to consider whether they really want to move ahead, given the costs.
The project sponsor may wish to reconsider the project or reduce its scope once he or she sees the cost estimates. If the sponsor is unwilling to fully fund the budget, the project manager—and anyone else accountable for the success or failure of the effort—may wish to withdraw. Projects that aren't fully funded stand little chance of succeeding.
Once you've launched your project, use the budget to monitor progress. Do this by comparing the actual outcomes of your project with the budgeted outcomes. Use your findings to take timely, corrective action to get a wayward project back on track.
Take a Moment
Take Action
第 6 节
Test your understanding and reinforce what you’ve learned.
Try it Out
答案与解析
A PERT chart.(正确)
The PERT chart shows all tasks in progress at a given time and the dependencies between outcomes, tasks, and events. They are useful for assessing the impact of a change in one area on the rest of a project.
A bar chart.
Bar charts show project progress but don’t show task dependencies or how changes in one area impact the rest of the project.
A Gantt chart.
Gantt charts provide a "big picture" view of the project but don’t show task dependencies or their impact on the project.
A flowchart.
Flowcharts are good for managing detailed information but don’t show task dependencies or the impact of one task on another.
第 7 节
Reflecting on your learning helps you apply relevant concepts to your job.