Develop a Schedule and Budget 查看中文版

第 1 节

You start defining a project schedule during the buildup phase of the project management process. To define your project schedule, begin by determining the latest date for completing your project—a date that can't be changed. Work backward from that date to see when you and your team will need to provide interim deliverables.

Develop a Schedule and Budget

You're responsible for producing the annual report for your organization's shareholder meeting. You know it will take the printer two weeks to print the report. That means all the final art and copy for the report must be ready to send to the printer two weeks before the meeting. Develop a Schedule and Budget

During the implementation phase, you will closely monitor the schedule you've created. If conditions change, you'll likely need to adjust your schedule.

Develop a Schedule and Budget

The shareholders' report project moves into the implementation phase, and the team starts developing the artwork and text. Then you learn that the printer will need more time to print the report because of unplanned maintenance work on its presses. So you adjust your schedule to stipulate that the report's files will have to go to the printer three weeks before the shareholders' meeting, not two weeks. Develop a Schedule and Budget

第 2 节

  1. Use the Work Breakdown Structure or a similar outline to develop a list of specific activities or tasks.
  1. Assign a deliverable to each activity—for instance, "rough draft of survey questions" or "prototype for test market" or "beta version."
  1. Use deliverables as a basis for creating a project schedule with realistic milestones and due dates.
  1. Identify bottlenecks that could upset the schedule.
  1. Determine ways to remove bottlenecks or build in extra time to get around them.
  1. Establish control and communication systems for updating and revising the schedule.

Make a Connection

1. Think about a recent project you or your team managed. What steps did you follow when drafting your project schedule?

第 3 节

Critically examine your draft schedule. Seek ways to make it more accurate, more realistic, and tighter. Look for:

  • Errors. Are your time estimates realistic? Pay particular attention to time estimates for tasks on the critical path. If any of these tasks cannot be completed on time, the entire schedule will unravel. Also, review the relationships between tasks. Does your schedule reflect tasks that can start simultaneously and those that can't start until some other task is completed?

  • Oversights. Have you left out any tasks or subtasks? Have you overlooked time for training and maintenance?

  • Overcommitments. Will some employees have to work 10 to 12 hours per day for months on end to complete the tasks assigned to them? Are you expecting a piece of equipment to perform in excess of its known capacity? If so, remove such overcommitments—for instance, by redistributing the workload.

  • Bottlenecks. Will work necessary for a particular task pile up at that point in the process? Think of an auto assembly line that has to stop periodically because the people who install the seats cannot keep up with the pace of the line. To remove bottlenecks, speed up the work process used in that task or shift resources into that task—for example, by adding people who have some slack time in their responsibilities.

Tips for scheduling your project

Know which deadlines are rigid and which have some flexibility. Don't schedule more detail than you can actually oversee yourself. Develop schedules according to what's logically possible. Allocate resources later.​​​​​​​ Record all time segments in the same increments, such as days or weeks.​​​​​​​​​​​​​​​​​​​ Don't schedule a project so that overtime is needed to meet original target dates. That doesn't leave any flexibility for handling problems that might come up later. Tips for scheduling your project

第 4 节

Managers use several different kinds of tools to create draft schedules. These include bar charts, flow charts, and PERT charts.

Bar charts

Bar charts show project stakeholders how a project is progressing. A Gantt chart is one example. A Gantt chart is simple and shows the "big picture" of a project at a glance. It lists project tasks in the left-hand column and indicates time blocks for each. These blocks indicate when each task should begin, based on task relationships, and when it should end.

Sample Gantt Chart

Gantt charts show the following:

  • Task status; completed tasks are shaded out

  • Estimated project duration

  • Estimated task duration

  • Task sequences and tasks completed in parallel

But Gantt charts don’t show task dependencies—that is, which task must be completed before another begins. Thus, these charts make it difficult to assess the impact of a change in one area on the rest of a project.

Flow charts

Flow charts help your team closely manage and communicate project details to your supervisors and project team members. A critical path diagram is one example. This kind of diagram shows your project's critical path: the set of tasks that determines total project duration. The critical path is the longest sequence of tasks through the project. Any delays in the critical path will delay completion of the entire project. By identifying the critical path for your project, you can allocate resources efficiently.

sample critical path diagram

PERT charts

A PERT (performance evaluation and review technique) chart shows when every project task within a phase should begin, how much time is scheduled for each task, and when each task should be completed. The chart also shows all tasks in progress at a given time and all the dependencies between outcomes, tasks, and events.

Sample Pert chart

In the PERT chart, each task is represented by a node that connects with other nodes, or tasks, required to complete the project. While a PERT chart indicates the important task dependencies of a project, a downside is that the chart can be complex and difficult to master.

无论多么有经验,你都需要一个项目计划 why you need a project plan

哈佛教授讲授视频逐字稿
My entire career, I've been managing projects of some sort or another. And I had a lot of experience, of course, but I'd also received a lot of feedback that I was good at managing projects. And it actually seemed to be something that was a natural skill, that I really just innately understood what needed to be done and when and how to engage with people. So I was pretty confident in my project management abilities. Probably overconfident. And a couple years ago I was working on a case with a medical device client. And they were looking at doing something really, really different; really bringing something new into the operating room. And it felt pretty similar to a lot of other projects that I had done, so I thought, "I've done this before. I don't need to worry about it, I can manage all of this in my head." I was definitely wrong and should have known that I was going to be wrong because the project had been organized into sprints, and there were clear milestones where I had no influence over the timing or what needed to be presented. But still I thought I could manage everything in my head. And I was--as I said--I was completely wrong because I hadn't expected the unexpected: all of those little emergencies and things that can crop up during the day, the personality conflicts that can happen within teams that can really distract a project manager and can derail the work. So it came to be a couple days before our first big client meeting and I realized nothing had gotten done. And the stuff that was done wasn't at an acceptable quality. So we just started throwing things together, hoped for the best, went into that client meeting. We were staring down a room of executives and clinicians and engineers and scientists, asking them if they could come up with what the needs of patients and of surgeons and of hospital executives would be. And we were just getting met with blank stares. So we're really sweating things, and then a minor earthquake happened and we had to evacuate the building. And that really put an end to the meeting, but it really kind of made me realize what dire straits we were in, in terms of the project, and that we needed a project plan in order to get the project back on track and keep it on track. I realized I couldn't rely on an earthquake to save me the next time this happened, and that what I really needed to do was use the tools that were available to manage the project and not just rely on experience in order to keep things going as they should.

Use scheduling tools flexibly

Choose the scheduling tool that best suits you and your project. You'll probably end up using different kinds of tools at different times, depending on whether you want to show:

  • What has to be done

  • How long a particular activity will take

  • In what order each activity has to happen

  • Who is responsible for each activity

Bar charts are good for showing stakeholders and end users how the project is progressing. Flow charts are good for closely managing and communicating detailed information to supervisors and people doing the work. PERT charts are good for showing important task dependencies.

But the best tool for managing a project is the one you're most comfortable with. Don't be lured into using a tool just because "everyone else does" or because it's "cutting-edge." To pick the best method for you, use your experience. Look at the system you use for tracking your own work, and consider how satisfied you are with it. That can help you decide whether to stay with your current system or try some new ones.

Tips for selecting project management software

There are lots of project management software applications available today. But remember: Software is not infallible. It won't be able to check for faulty logic when it's putting together a schedule for your project. So once your software program or application has developed a schedule for your project, review the schedule carefully with another team member or stakeholder. Then finalize it. When you're selecting project management software, look for applications that can: Handle development of and changes to Gantt charts, critical path diagrams, and PERT charts Provide on-screen viewing of information before you print Produce schedules and budgets Integrate project schedules with a calendar allowing for weekends and holidays Let you create different scenarios for contingency planning and updating Warn you of any overscheduling of individuals and groups Tips for selecting project management software

第 5 节

A budget is the financial blueprint or action plan for your project. It translates the project plan into measurable expenditures and anticipated returns over a certain period of time. Your success as a project manager, as well as the success of your project itself, will be measured in part on whether you complete the project within the budget.

Creating your budget is something you do during the buildup phase of the project management process. However, you may have to adjust your budget during the implementation phase if circumstances change.

To develop your project budget, first ask yourself: What is it going to take—in terms of resources—to successfully complete this project? To determine the cost of the project, break it down into the key cost categories you anticipate.

Typical project costs

Identify the cost categories, also known as line items, relevant for your budget. Typical project cost categories include:

  • Personnel. This is almost always the largest part of a project's budget. It includes full-time and temporary workers.

  • Travel. People may have to travel from one location to another to do their project work. Consider whether everyone will be on-site, or whether the team will need to gather at one locale. Remember to budget for meals and lodging.

  • Training. If training will be required, determine whether it will take place on-site, or whether travel expenses will be involved. If you plan to hire an outside contractor to provide the training, make sure your budget reflects his or her fees and expenses.

  • Supplies. In addition to the usual—computers, pens, papers, software—you may need unique materials.

  • Space. If some people may have to be relocated to other facilities, estimate how much room and money that would require.

  • Research. Consider whether you'll have to buy studies or data to support your project versus your team performing such research itself.

  • Professional services. If you'll have to hire a market research firm, bring in a consultant, or seek legal advice, reflect those costs in your budget.

  • Capital expenditures. You may need equipment or technical upgrades to complete the project. Some of these capital expenditures will need to pay for themselves.

Review and refine the initial cost estimates you made during the planning phase of your project. And remember that a budget, no matter how carefully planned, is still just your best guess. Be prepared for actual numbers to deviate from your original estimates. And stay as flexible as possible within your limitations of time, quality demands, and total money available.

Often-overlooked costs

Consider often-overlooked costs that could affect your project budget. Examples include:

  • Training costs after the project is completed to teach users to implement your project

  • Ongoing personnel and maintenance costs once the project is complete

  • Insurance

  • Licensing fees

  • Costs for outside support such as accounting or legal counsel

Contingency funds

Many project budgets contain some degree of flexibility. That's because it's extremely difficult to anticipate every expense in a project. To give your budget some flexibility, build in contingency funds—for instance, you might ask for 5% of the estimated project budget for contingency alone. This allows you to accommodate some unanticipated costs without having to ask for more funding later.

Should your project proceed?

To build your project budget, you estimate costs before the work actually begins. So creating the budget gives everyone a chance to consider whether they really want to move ahead, given the costs.

The project sponsor may wish to reconsider the project or reduce its scope once he or she sees the cost estimates. If the sponsor is unwilling to fully fund the budget, the project manager—and anyone else accountable for the success or failure of the effort—may wish to withdraw. Projects that aren't fully funded stand little chance of succeeding.

Once you've launched your project, use the budget to monitor progress. Do this by comparing the actual outcomes of your project with the budgeted outcomes. Use your findings to take timely, corrective action to get a wayward project back on track.

Take a Moment

1. Think about the budget for a project you worked on. What were two or three of the most prominent project costs?

Take Action

1. What action will you take next to build a realistic project schedule and budget?

第 6 节

Test your understanding and reinforce what you’ve learned.

Try it Out

1. You work for a successful regional bank. You have been assigned to develop a new loyalty rewards program and integrate it throughout the bank. You need a reporting tool that will help each department monitor how its part of the product launch affects other departments—and how it is affected by other departments. Which scheduling tool would be the most appropriate?
答案与解析

A PERT chart.(正确)
The PERT chart shows all tasks in progress at a given time and the dependencies between outcomes, tasks, and events. They are useful for assessing the impact of a change in one area on the rest of a project.

A bar chart.
Bar charts show project progress but don’t show task dependencies or how changes in one area impact the rest of the project.

A Gantt chart.
Gantt charts provide a "big picture" view of the project but don’t show task dependencies or their impact on the project.

A flowchart.
Flowcharts are good for managing detailed information but don’t show task dependencies or the impact of one task on another.

第 7 节

Reflecting on your learning helps you apply relevant concepts to your job.

Take a Moment

1. 1. What new insights do you have that could benefit you or others in your workplace?
2. 2. What are your biggest opportunities for applying concepts from this Lesson in your workplace?

Further reading

项目驱动型组织的 10 个关键问题解答
如今,项目与各类举措已成为战略执行和价值创造的主要方式。为应对这一挑战,一种全新的企业模式——项…
推动变革,塑造“项目驱动型组织”
在持续变化的环境中,项目正成为企业演变、适应与发展的方式。战略依托项目落地,创新借由项目实现。这一点在 2020 年变得…
代理式 AI 项目为何会失败——以及如何让你的项目取得成功
代理式 AI 拥有变革性的潜力,但这只属于那些能够以严谨态度和明确战略意图应对的组织。市场不会奖励那些仅仅为了技术而追逐…

Top 3 in the source platform's original order