Pocket Leadership口袋领导力

Project Management

Monitor Project Progress and Problems 查看中文版

第 1 节

Project monitoring happens during the implementation phase of the project management process. As you monitor your project, you assess progress toward the project's objectives and address any challenges that come up. These could include problems within your project team or difficulties with schedule, budget, or quality of your project's outcomes.

Worksheet for Monitoring Project Progress

附件:worksheet_for_monitoring_project_progress(docx · 1197 KB,本地副本)

第 2 节

If you're managing a sizable project with plenty of meetings and many participants, systematically keep track of decisions, assignments, and action items. Many organizations use meeting minutes—notes recorded by an appointed individual—for this purpose. The minutes are reviewed and approved at the next meeting and amended if necessary. Approved minutes then go into a file, and participants can consult them as needed.

In addition, make the most of milestones—significant events in a project—to remind team members of how far they've come and how much further they must go. Examples of milestones include:

  • The successful testing of a product prototype

  • Installation and successful testing of a critical piece of equipment

  • Delivery of finished components to the stockroom

  • Completion of the project—the ultimate milestone

Use milestones as occasions for celebrating progress; for instance, with a group luncheon or an outing.

项目管理中少为人知的第二类跟踪 the equation for change

哈佛教授讲授视频逐字稿
When people think about project management, they tend to think about Gantt charts, an elaborate matrix of who's going to do what when, and tracking spending, tracking finances, tracking deadlines, making sure everything gets done. And it's true all of those things are really important. But one of the things that often gets forgotten is, are you in fact managing the impact that the project is having, particularly in the arena of change, and the effect of the project on people and on the organization? Most projects are in fact creating change of some kind. Either they're creating change by the nature of the technology or the project--the content of the project--or they're creating change in terms of the impact on the larger environment on the organization. So one of the things that I've found really useful in project management is tracking what I think of as the major three components of a change effort. They derive from a kind of age-old axiom called the "equation for change," which says that you get change in an organization or a person when you have a clear picture of where you're going, when you have an understanding of felt pain, a sense of motivation of why we need to change, and a very clear idea of what to do next; that is, "What am I going to do differently?" And so when I'm thinking about a project, particularly a large project like the installation of a new IT system or the moving of a building or changing the location of an organization to another building—those kinds of projects—it's really important to pay attention to these three activities: mapping out not only against time and people and money, but also: "Are we doing, every week of this project, things that are strengthening and reinforcing the vision of where we're going? Are we doing things every week in this project that are helping people understand why they have to change, what the pressure is to change, what the advantage is of the change? And are we doing things every week, on a regular basis, that help people get ready to take the next step, to know what to do next?" I find that when we track a project in that way, as well as in the traditional ways, we have a much greater likelihood of success and a positive outcome. And we get great feedback from people who are affected by the project. They in fact are reminded why they have to do this. They're reminded of what's going on, and the need to change. And they're reminded of what it is that they in fact need to be doing differently, right now, on Monday morning. So I encourage people to do both kinds of tracking on project management.

Poll

Poll

Make a Connection

1. How do the project teams you work with keep track of decisions, action items, and assignments?

第 3 节

As your project's implementation proceeds, identify any team challenges that affect productivity and move swiftly to resolve them. Here are some examples of team problems you might encounter and how you might address them:Managing Projects: Expert Solutions to Everyday Challenges. Pocket Mentor Digital. Boston: Harvard Business School Publishing, 2006: 41.

address_team_challenges_table

address_team_challenges_table

第 4 节

Compare the actual spending for a given period during your project implementation with the spending specified in your budget. If actual spending is higher than what you budgeted, identify the cause. Then take corrective action.

Factors that can send your project over budget include:

  • Failure to factor in currency exchange rates or exchange-rate fluctuations

  • Unexpected inflation during long-term projects

  • Lack of firm prices from suppliers and subcontractors

  • Estimates based on different costing methods, such as hours versus dollars

  • Unplanned personnel costs incurred to keep the project on schedule, including increased overtime

  • Unexpected space or training needs

  • Consultant or legal fees needed to resolve unforeseen problems

第 5 节

Highlight milestones in your project schedule and use them to monitor progress. Track the following aspects of your project schedule:

  • Hours. How much work has been expended on any given activity? Does the number of hours expended match the number specified in your budget? If not, why not?

  • Activities. Which activities have been worked on? When did they start? Are they complete? Were they finished on schedule? If not, why not?

  • Milestones. Have milestones been met? If so, which ones? If not, why not?

  • Deliverables. Have deliverables been completed on time? Did they meet quality standards? What caused any shortfalls?

Delays can be caused by vague project objectives or an overly optimistic schedule. Scheduling problems can also result from an incomplete project plan, failure to manage risks, or lack of proper tracking and control.

If your project experiences scheduling problems, find out what's causing them. Then take corrective measures. That might mean asking for additional resources, putting the schedule on an accelerated course, or persuading the project sponsor to accept the delay.

Tips for controlling project delays

Managing Projects: Expert Solutions to Everyday Challenges. Pocket Mentor Digital. Boston: Harvard Business School Publishing, 2006: 67.
Renegotiate. Discuss with stakeholders the possibility of extending the deadline. Use later steps to recover. Reexamine budgets and schedules to see if you can make up the lost time elsewhere in the project. Narrow the project scope. Drop nonessential elements of the project to save time. Deploy more resources. Put more people to work on the project. Seek alternative sources. Look for another source to supply a missing item. Accept partial delivery. Accept fewer of a needed item to keep work going, and complete the delivery later. Offer incentives. Offer bonuses or other incentives for on-time delivery of needed resources or on-time completion of critical tasks. Tips for controlling project delaysManaging Projects: Expert Solutions to Everyday Challenges. Pocket Mentor Digital. Boston: Harvard Business School Publishing, 2006: 67.

第 6 节

Watch for signs of "scope creep"—stakeholders asking you to address more and more problems throughout implementation of your project. Revisit the scope you originally defined for your project.

If stakeholders insist that the project accomplish more than its original intent, discuss the potential impact on project time, cost, and quality of outcomes. Clearly point out any trade-offs that must be made.

第 7 节

To check quality during your project's implementation, examine some unit of work at an appropriate point to ensure that it meets specifications. Inspect deliverables using the most appropriate tools, such as detailed inspections, checklists, and statistical sampling. Depending on costs, determine whether any rejected deliverables can be returned or reworked.

Monitor Project Progress and Problems

Your project entails building a new e-commerce site. You decide to test each component of the software system as it's developed. That way, you can see as early as possible if the components are functioning. Monitor Project Progress and Problems

Periodic quality checks uncover conditions that are out of specifications. Once you've identified these problems, your project team can figure out what's causing them and take action to address them.

Tips for creating a project control system

Budgets, quality checks, and milestones are the basic components of a project control system. To use them: Focus on what's most important. Which parts of the project are the most crucial to track and control? Where are the essential points at which we need to place controls? Build corrective action into the system. Your control system must use information gleaned from your monitoring efforts to initiate corrective action. Otherwise, all you're doing is monitoring. Don't let control lapse into micromanagement. Encourage the people closest to the problem to make needed corrections. Emphasize timely responses. Corrective actions require real-time, daily, or weekly information about what's going on with your project. No single control system is right for all projects. A system that's right for a large project will swamp a small one with paperwork. A system that works for small projects won't be robust enough for a big one. So, find the one that's right for your project. Tips for creating a project control system

In this activity, choose the best approach to addressing problems and improving quality.

Try it Out

1. How should Tamika effectively address the quality problem?
答案与解析

A. Tamika should provide training to develop her team’s time management skills.
Not the best choice. While improving time management skills is always helpful, the team is quickly approaching their deadline. Pulling them away from their work at a stressful time will only exacerbate the problem.

B. Tamika should schedule time with the team to clarify quality expectations and answer any questions they may have.(正确)
Correct choice! Clarifying quality expectations and standards will ensure that Tamika and her team are on the same page, reducing the likelihood that a communication mistake will jeopardize their ability to meet the deadline.

C. Tamika should encourage her team members to take breaks more frequently so they can recharge.
Not the best choice. While taking breaks is a good way to alleviate employee burnout, directly addressing the problem would be a more effective solution.

2. What approach should Tamika take in addressing the missed milestone?
答案与解析

A. Tamika should inform stakeholders that the project will be delayed.
Not the best choice. While it’s critical to inform stakeholders about the project’s status, Tamika first needs to address the reasons for the delay. Also, rather than simply telling stakeholders that there will be a delay, Tamika could try to negotiate with them to adjust the schedule or agree to partial delivery.

B. Tamika should wait to see if the team can make up for lost time in the second half of the schedule and get the project back on track.
Not the best choice. When Tamika identifies the root cause of the schedule delay, she needs to take corrective action. Doing nothing isn’t a smart plan. Tamika could reexamine the schedule to see if work could be made up elsewhere in the project—but this still requires action.

C. Tamika should deploy more resources to the project to assist the team in meeting the deadline.(正确)
Correct choice! Tamika should explore adding resources to the project to meet the schedule, or even seeking alternative sources for fulfilling a portion of the project demands. If there’s no room in the budget for additional resources, then Tamika can choose another option, such as negotiating with stakeholders to revise the schedule or permit partial delivery of the app’s capability.

3. What approach could Tamika take to improve the monitoring of quality next time around?
答案与解析

A. Tamika should establish weekly quality checks to ensure that specifications are being met.(正确)
Correct choice! By examining units of work on a consistent basis, Tamika and the project team will be able to identify and mitigate problems before they occur.

B. Tamika should implement a quality monitoring system to continuously oversee each aspect of the project.
Not the best choice. Though quality checks are essential, it isn’t necessary to monitor every step of the project. Tamika needs to trust the team to handle the details and focus on tracking the parts of the project that are most crucial to success.

C. Tamika should establish a group of specialists external to the team who can be ready to take corrective action in case something goes wrong with the product’s quality.
Not the best choice. Tamika shouldn’t let project supervision spiral into micromanagement. She should encourage the people most familiar with the project to make necessary corrections, rather than people who are distant from it.

Take Action

1. What action will you take next to keep projects on schedule and within budget?

第 8 节

Test your understanding and reinforce what you’ve learned.

Try it Out

1. Your team has just begun redesigning an electrical utility’s billing system, and already you can see challenges: Your team members seem to be wasting time on the wrong tasks. What course of action would best help solve the problem?
答案与解析

Clarify the quality expectations for the team.
This is more appropriate when team members are delivering poor-quality work.

Help team members readjust their work schedules.
Adjusting work schedules is more appropriate for addressing burnout.

Assign tasks to two members to work on together.(正确)
If team members are spending time on the wrong tasks, assign tasks to pairs and emphasize which ones are most important.

Encourage team members to take a break and recharge.
Encouraging breaks is more appropriate for dealing with burnout.

第 9 节

Reflecting on your learning helps you apply relevant concepts to your job.

Take a Moment

1. 1. What new insights do you have that could benefit you or others in your workplace?
2. 2. What are your biggest opportunities for applying concepts from this Lesson in your workplace?

Further reading

项目驱动型组织的 10 个关键问题解答
如今,项目与各类举措已成为战略执行和价值创造的主要方式。为应对这一挑战,一种全新的企业模式——项…
推动变革,塑造“项目驱动型组织”
在持续变化的环境中,项目正成为企业演变、适应与发展的方式。战略依托项目落地,创新借由项目实现。这一点在 2020 年变得…
代理式 AI 项目为何会失败——以及如何让你的项目取得成功
代理式 AI 拥有变革性的潜力,但这只属于那些能够以严谨态度和明确战略意图应对的组织。市场不会奖励那些仅仅为了技术而追逐…

Top 3 in the source platform's original order