Follow six steps to create your implementation plan:

BusinessCaseDevelopment_CreateAnImplementationPlan_Infographic

〔图表类内容,图片原件见线上原文〕

第 2 节

Your implementation plan lays out your process for tracking your progress and measuring the success of your proposed solution.

Many managers think of implementation plans as lists of action items, due dates, and the people responsible for them. While decision makers reading your business case will want to know this information, they’ll also want to know:

  • The primary milestones

  • The individuals responsible or accountable for each milestone

  • The resources required to reach each milestone

  • Dates when the company will see the benefits of your recommended course of action

  • Impacts on the company’s expense and human resources budgets

  • Increases in revenue

  • Your plan for demonstrating that the solution’s intended results have been realized

Try it Out

Try it Out Think of a time when you created a plan to track progress and measure the success of a proposed initiative. Pick all of the actions you took.

Make a Connection

1. If you answered "No" to any of the items above, what will you do to create a more effective plan in the future?

第 3 节

To draft your implementation plan, list your high-level milestones: the major steps needed to carry out your solution. When listing your milestones:

  • Keep it simple. Avoid details of how you will accomplish each milestone.

  • Include notes describing how you plan to address risks you identified earlier.

  • Adopt a phased approach. If there are definable phases to the project, list your milestones by phase.

案例

After analyzing alternatives and considering risks, Sydney proposes working with a consultant to help with training the sales team in solution selling. In drafting her implementation plan, Sydney proposes five milestones: Phase 1 (1 month). Hire the consultant using the vice president of procurement to negotiate the contract. Phase 2 (6 months). Develop training, conduct pilot training, evaluate pilot, and collect sales results. Phase 3 (3 months). Roll out training to all sales people and sales coaches. Phase 4 (1 month). Track results; forecast improvement in sales, customer value, and employee turnover to establish business results targets for the next year. Phase 5 (ongoing). Modify financial targets for sales on an ongoing basis.

第 4 节

When you present your milestones to decision makers:

  • Anticipate negotiations about the time frame. Expect that they will want the project done sooner than your estimated delivery date.

  • Be prepared with a backup plan. Describe an alternative scenario in which phases are completed more quickly. If this is not feasible, develop an argument that shows why accelerating the project implementation would be too risky and wouldn’t achieve the intended results.

Depending on the size of your proposal, consider establishing checkpoints with decision makers at the end of each phase to assess progress toward your stated goals.

第 5 节

Think about each phase of your project. Which resources will you need to accomplish each one? Show any movement of budget dollars and headcount in your implementation plan, or decision makers may assume you will fund the initiative from your current budget.

案例

Sydney shows that she will need help from procurement to develop and monitor the contract between Satellite and the consulting firm. She will also need $2 million added to her budget to pay for the consulting contract.

第 6 节

Many implementations are unsuccessful because managers don't assign accountability for milestones or fail to gain commitment from the necessary individuals.

案例

Sydney knows she'll need someone from procurement to negotiate the consulting contract. But if she doesn't confirm up front that the department can provide a specific person, she may be left empty-handed when the contract negotiation phase begins.

In your implementation plan, name the individuals who will do each phase of the work. Also indicate who will be responsible for ensuring that each phase of the project realizes its intended results in terms of costs, revenues, benefits, and deliverables. More than one person may share this responsibility.

Decision makers will also want to know what burdens they'll have to shoulder to ensure your proposal’s success.

案例

Satellite’s sales group would need to increase their forecasted revenue commitments to justify the cost of hiring the consulting firm.

第 7 节

Decision makers reviewing your business case want to know when they can expect your solution to generate the promised benefits. To answer this question, examine your data and identify the results you expect to see during implementation of your idea.

案例

While Sydney expects sales revenue to increase by $7 million once her solution is fully implemented, she doesn’t anticipate it will rise immediately. She believes that 10% of the annualized $7 million (or $175,000) will be realized in Q3; 30% (or $525,000) in Q4 of year one; 60% in year two ($4.2 million); and the full $7 million at the end of year three.

In estimating payoff dates, remember to plan for a gap between when results occur and when they are officially recorded. Though your plan might generate the expected results during the expected period, those results may not get recorded in your company's performance management system until the next period.

第 8 节

If your recommended course of action is approved, your organization will ask you to report on the project's successes and shortfalls regularly. By keeping track of estimated due dates versus actual delivery dates, as well as estimated benefits versus actual benefits, you generate the data you'll need to garner support for your project through each milestone.

Whether your results prove better or worse than your expectations, identify the causes behind any major deviation from your business case proposal. By understanding what worked and what didn’t, you can learn what to do differently or what successful practices to continue in the future.

Tips for drafting your implementation plan

Include measurable milestones. Your milestones should be clearly defined and easily measured—for example, “ Develop pilot training content” or “ Conduct market testing.” Use generic dates. For example, “year 1” or “six months from contract approval.” Set a realistic schedule. Managers often underestimate the time they’ll need to implement their recommendation. Assign individual accountability. Use specific names, not just department names or position titles, when assigning accountability for a task or committed result. Keep track of your resources. Consider the resources you’ll need for each milestone and whether they will be available when you need them. Tips for drafting your implementation plan

Project Implementation Tracking Form

附件:project_implementation_tracking_form(docx · 1174 KB,本地副本)

Try it Out

1. Why might Eric's boss view this implementation plan as flawed?
答案与解析

A. There is no need to test the technology prior to deployment and conducting the test would only add unnecessary expense and time.
The proof of concept for the chosen technology is a necessary step in the implementation of Eric's solution.

B. Eric's boss does not believe she should have to monitor the success of the project.
This is a costly and important project. Eric's boss would likely be very interested in assessing its performance.

C. There should be more check-in meetings interspersed throughout the timeline.(正确)
A single check-in meeting at the end of the timeline is not adequate to monitor the progress of this complex, expensive project. By having more frequent check-in meetings, Eric and his boss will have more opportunities to address any difficulties that emerge as the solution is implemented, and Eric's boss could offer guidance when necessary.

2. What would have prevented this confusion?
答案与解析

A. The IT staff should have communicated their training needs to Eric more clearly, since they were the ones who would be responsible for learning the new security protocols.
The IT staff had no reason to assume that they would be responsible for obtaining the resources necessary for the training, since the training could have come from several possible sources.

B. Eric should have specified in his implementation plan who would be responsible for providing the training, since he was the one who advocated for the training.(正确)
A crucial step in building an implementation plan is explicitly defining who is responsible for each milestone and who will procure needed resources. If Eric had taken this step, the HR department could have prepared for this responsibility or alerted Eric to any difficulties in doing so.

C. The HR staff should have prepared for this responsibility ahead of time, since they were the group with the skills, knowledge, and personnel to provide the needed training.
The HR staff had no reason to assume that they would be responsible for providing the training, since the training could have come from several possible sources.

3. What might have caused the disparity between the expected and actual gains?
答案与解析

A. The financial predictions in Eric's implementation plan were too conservative
Realizing benefits beyond the predicted gains (not less than the predicted gains) indicates an overly conservative plan.

B. Eric didn't plan for a lag between the time when results occur and when they are recorded(正确)
With increased customer satisfaction with Glasswell's improvements, any gains in revenues will likely be seen in future quarters as revenue reporting catches up with the results generated. It is too early to declare the project a failure.

C. The company tracked the wrong metrics
Revenues and customer retention are two important measures of the company's health, so these are appropriate metrics to track.

Take Action

1. What action will you take next to create an implementation plan for your business case proposal?

第 9 节

Flaws in your implementation plan can cripple your business case. See if you can spot the flaws in an implementation plan and fix them.

Eric has decided to solve Glasswell Optics' website problems by distributing the customer database to a different hosting company. He must now create an implementation plan for the project. He breaks the project timeline into phases—including conducting a proof of concept for the chosen technology, training the IT department on new security protocols, rolling out services to the new host, and tracking system performance and customer satisfaction for three months following the upgrade. He also plans a check-in meeting with his boss to evaluate the success of the project.

Eric's implementation plan calls for training IT personnel on the new security protocols. But when it comes time to provide this training, confusion arises. Eric had assumed that the human resources department would facilitate the training. But the HR department thought Eric would coordinate the training himself. The IT department wants to hire a contractor, an expert with the new systems, to do the training.
When Eric's solution is implemented, the Glasswell Optics website provides uninterrupted service, and customers approve of the new security measures. In his implementation plan, Eric predicted that his solution would result in a 10% increase in customer retention and $500,000 in new business generated within the first quarter after the upgrade. But despite the outward signs of success, the predicted first-quarter gains don't materialize.

第 10 节

Reflecting on your learning helps you apply relevant concepts to your job.

Take a Moment

1. 1. What new insights do you have that could benefit you or others in your workplace?
2. 2. What are your biggest opportunities for applying concepts from this Lesson in your workplace?

Further reading

是时候让你的企业投资 AI 了:关键在于如何落地
企业应当如何思考在 AI 能力上的资源投入?问题早已不再是“自建还是外购”这样非此即彼的选择,而是要在四种不同路径之间进…
重新评估生成式 AI 的成本与收益
生成式 AI 有望为组织及员工个人带来巨大的价值。不过,当我们仅仅关注 AI 产出的价值时,往往很少考虑其他价值的来源。…
选择合适的生成式 AI 项目的框架
生成式 AI 已激发公众的无限遐想。这项技术几乎能即时生成初稿和创意,但也可能在准确性及伦理问题上存在缺陷。企业在追求其…

Top 3 in the source platform's original order